From: Purciarello, Gerard
Sent: Wednesday, March 23, 2011 11:37 AM
To: Titus, Brett
Cc: Casto, Greg; Gardocki, Stanley
Subject: Delayed Projects due to the Japan Event

Brett,
The following projects could be delayed due to SBPB coverage in the Ops Center (G. Casto since Mar 11 and S. Gardocki starting soon)
1) Peach Bottom LAR for Nitrogen Storage -Final SER could be delayed (Gardocki will be assigned to Ops Center)
2) TMI Main Steam Safety License Amendment Request -SER delayed (Gardocki will be assigned to Ops Center)
3) Palo Verde LAR for ADV change-Possible delay (Gardocki in Ops Center)
4) Update RG 1.137, Diesel Generator Fuel Oil, (delay due to Purciarello as Acting BC) NRO contacted to take the lead
5) Limerick License Amendment SER -possible delay due to Purciarello as Acting BC)
6) Seabrook License Renewal SER, final approval- delay due to Casto in Ops Center, Purciarello Acting
7) Ft Calhoun Ultimate Heat Sink License Amendment Request-possible delay due to Purciarello as Acting BC)
8) Callaway Extension of Completion time for BOP ESFAS ( delay due to Casto and Gardocki in Ops Center )

Jerry Purciarello
Senior Reactor Systems Engineer
Balance of Plant
NRR, Division of Safety Systems
301-415-1105

Previous Article

FirstEnergy Defends Safety After Inspection Finds More Cracks at Davis-Besse Nuclear Power Plant

Next Article

March 23rd, 2011 – Response to what are we not getting done – Samuel Miranda

Leave a Reply