From: Galloway, Melanie
Sent: Wednesday, March 23, 2011 11:47 AM
To: Ruland, William
Cc: Holian, Brian; Cheok, Michael; Lubinski, John
Subject: Impact on work from Japanese event response

License Renewal Delays:
* Follow-up safety RAIs for Seabrook will be delayed by two weeks. Potential to delay SER issuance.
* Draft of Information Notice related to torus degradation issues will be delayed by one month.
* Contractor-developed NUREG on structures degradation issues will be delayed by one month.

Impacts to LR from other Divisions (which you may have been provided separately by those Divisions):
* Pilgrim supplemental SER issuance will be delayed from April 11 to mid-May. (DCI)
* SAMA RAIs for Davis-Besse will be delayed by one week. Should not delay SEIS issuance. (DRA)