March 14th, 2011 – Looks like RCIC at Fukushima Daiichi Unit 2 has failed.

Author: No Comments Share:

From: Pannier, Stephen,
Sent: Monday, March 14, 2011 10:21 AM
To: King, Mark; Garmon-Candelaria, David
Cc: NRRDIRS Distribution
Subject: RE: NISA in English – LATEST INFO ON JAPANESE REACTORS / ON-GOING NUCLEAR EMERGENCY

From the most recent TEPCO release, looks like RCIC at Fukushima Daiichi Unit 2 has failed…

http://www.tepco. co.jp/en/press/corp-com/releasell 1031403-e. html

From: King, Mark \VX(-
Sent: Monday, March 14, 2011 6:52 AM
To: Garmon-Candelaria, David
Cc: NRRDIRS Distribution
Subject: FW: NISA in English – LATEST INFO ON JAPANESE REACTORS / ON-GOING NUCLEAR EMERGENCY

FYI

From: King, Mark
Sent: Monday, March 14, 2011 6:50 AM
To: Thomas, Eric
Subject: FW: NISA in English – LATEST INFO ON JAPANESE REACTORS / ON-GOING NUCLEAR EMERGENCY

March 14, 2011
Japanese Nuclear and Industrial Safety Agency (NISA) – An explosion caused by hydrogen at Unit 3 of Fukushima Dai-ichi NPS (the 2ndrelease
TEPCO reported NISA that there was an explosion at Unit 3 of Fukushima Dai-ichi Nuclear Power Station, NPS, at 11:01. According to TEPCO, the containment vessel of the unit was not broken. Detail information is under’investigation,.

The wind condition is calm and the direction of the wind above the station is the west or the southwest.

Residents living within the area at least 20 km radius from Fukushima Dai-ichi NPS are requested to shelter in buildings or _houses.

TEPCO reported to NISA that one person was injured at Fukushima Daiichi NPS at this time. TEPCO is preparing to transfer the person to Fukushima Dai-ni NPS. (Contact Person)

Mr. Toshihiro Bannai
Director, International Affairs Office,
NISA/METI
Phoie:+81-(0)3-3501-1087

SOURCE of above info: http://www.nisa.meti.qo.jp/enqlish/files/en20110314-2.pdf

NOTE: NEWS REPORTS SAY THAT SIX WORKERS WERE INJURED.

Source of below: http://www.nisa.meti.go.jp/english/files/en20110314-1.pdf
March 14, 2011

Nuclear and Industrial Safety Agency
Seismic Damage Information(the 22th Release)
(As of 07:30 March 14, 2Q11) – Japan Time
Nuclear and Industrial Safety Agency (NISA) confirmed the current situation of Onagawa NPS, Tohoku Electric Power Co., Inc; Fukushima Dai-ichi and Fukushima Dai-ni NPSs, Tokyo Electric Power Co., Inc. as follows:
1. The status of operation at Power Stations (Number of automatic shutdown units: 10) oFukushima Dai-ichi Nuclear Power Station, Tokyo Electric Power Co., Inc.(TEPCO)(Okuma-machi and Futaba-machi, Futaba-gun, Fukushima Prefecture)
(1) The status of operation
Unit 1 (460MWe): automatic shutdown
Unit 2 (784MWe): automatic shutdown
Unit 3 (784MWe): automatic shutdown
Unit 4 (784MWe): in periodic inspection outage
Unit 5 (784MWe): in periodic inspection outage
Unit 6 (1,100MWe): in periodic inspection outage
(2)- Readings at monitoring posts .
The measurement of radioactive materials in the environmental monitoring area near the site boundary by a monitoring car confirmed the increase in the radioactivity, compared to the radioactivity at 19:00, March 13.’MP1 (Monitoring at North End of Site Boundary):26 microSv/h(18:30 March 13) MP2 Monitoring at north- northwest of Unitl and northwest of the End of Site Boundary for Unit 1)
450 microSv/h(20:10 March 13)
-*680 microSv/h(3:50 March 14)
MP4 (Monitoring Car at North West Site Boundary for Unit 1)
44.0 microSv/h(19:33 March 13)
— 56.4 microSv/h(04:08 March 14)
(Surveyed by MP2 as MP1 is in the top of the cliff)
MP6 (Monitoring at the Main Gate)
5.2microSv/h(19:00 March 13)
–+66.3 microSv/h(02:50 March 14)
(3) Wind direction/wind speed (as of 00:01, March 14)
Wind direction: North North West
Wind Speed: 0.3 m/s
(4) Report concerning other malfunction
* No fire report notified to NISA

* TEPCO reported to NISA in accordance with Article 10 of the Act on Special Measures Concerning Nuclear Emergency Preparedness regarding Fukushima Dai-ichi, Units 1,2 and 3. (15:42 March 11)

– TEPCO report to NISA the event in accordance with Article 15 of the Act for Special Measures Concerning Nuclear Emergency Preparedness regarding Fukushima Dai-ichi, Units 1 and 2.(notified to NISA at 16:36 March 11)

– For Unit 1: Sea water is being injected to the Primary Containment Vessel (PCV) via the Fire Extinguishing System Line (Start up 11:55 March 13)

-+Interruption of injection (01:10 March 14)
* For Unit 2: Water Injection Function has been sustained. (14:00 March 13)
* For Unit 3: Fresh water is being injected to the PCV via Fireý
Extinguishing System Line (FESL) (11:55 March 13)
– For Unit 3: Sea water is being-injected to the PCV via FESL(13:12 March 13)
– For Unit 1 and Unit 3: Injection of Sea water injection into PCV is interrupted because of the lack of sea water in pit. (01:10 March 14)
– For Unit 3: Injection of Sea water into PCV is restarted(03:20 March 14) o Fukushima Dai-ni Nuclear Power Station (TEPCO)
(Naraha-machi/Tomioka-machi, Futaba-gun, Fukushima pref.)
(1) The status of operation
Unit1 (1,10OMWe): automatic shutdown
Unit2 (1,100MWe): automatic shutdown
Unit3 (1,100MWe): automatic shutdown, cold shut down at 12:15, March 12
Unit4 (1,100MWe): automatic shutdown
(2) Readings at monitoring post etc.
MP1 (Monitoring at the North End of Site Boundary)
0.036 microSv/h(19:00 March 13)
-0.038 microSv/h(05:00 March 14)
MP3 (Monitoring at the North/West End of site boundary)
0.038microSv/h(19:00 March 13)
-0.037 microSv/h(05:00 March 14)
MP4 (Monitoring at the North/West End of Site Boundary)
0.036microSv/h(19:00 March 13)
-+0.038 microSv/h(05:00 March 14)
MP5 (Monitoring at the West End of Site Boundary)
0.04 microSv/h(19:00 March 13)
-+0.042 microSv/h(05:00 March 14)
(3) Direction and velocity of wind (As of 05:00, 14 March)
Direction: South-southwest
Velocity: 0.9 m /s
(4) Report concerning other malfunction
• None of fire report notified to NISA
” TEPCO reported to NISA in accordance with Article 10 of the Act on
Special Measures Concerning Nuclear Emergency Preparedness
regarding Fukushima Dai-ni, Units 1. (18:08 March 11)
– As same as above, TEPCO reported to NISA Fukushima Dai-ni Units 2
and 4.(18:33 March 11)
4
. For Unit 1: Due to Recovery of Residual Heat Removal System(RHR),
water in suppression pool is started to cool for cold shut down.(01:24
March 14)
c. Onagawa Nuclear Power Station (Onagawa-cho, Oga-gun and
Ishinomaki-shi, Miyagi Prefecture)
(1) The status of operation
Unit 1 (524MWe): automatic shutdown, cold shut down at 0:58, March 12
Unit 2 (825MWe): automatic shutdown
Unit 3 (825MWe): automatic shutdown, cold shut down at 1:17, March 12
(2) Readings of monitoring post
Reading of monitoring post : Changed
MP2 (Monitoring at the North End of Site Boundary)
Approx. 10,000 nGy/h (as of 13:09 March13)
–*7,200 nGy/h (07:20 March 14)
(3) Report concerning other malfunction
– Fire Smoke on the first basement of the Turbine Building was confirmed
extinguished at 22:55 on March 11th.
– Article 10* of Act on Special Measures Concerning Nuclear Emergency
Preparedness (Unit No. not identified) (13:09 March 13)
2. Action taken by NISA
(March 11)
14:46 Set up of the NISA Emergency Preparedness Headquarters (Tokyo)
immediately after the earthquake
15:42: TEPCO reported to NISA in accordance with Article 10 of the Act on
Special Measures Concerning Nuclear Emergency Preparedness
regarding Fukushima Dai-ichi.
16:36: TEPCO judged the event in accordance with Article 15 of the Act for
Special Measures Concerning Nuclear Emergency Preparedness
regarding Fukushima Dai-ichi, Units 1 and 2.(notified to NISA at
16:45)
18:08: Unit 1 of Fukushima Dai-ni notified NISA of the situation of the
5
Article 10 of Act on Special Measures Concerning Nuclear Emergency
Preparedness.
18:33: Units 1,2 and 4 of Fukushima Dai-ni notified NISA of the situation of
the Article 10 of Act on Special Measures Concerning Nuclear
Emergency Preparedness.
19:03 : Government declared the state of nuclear emergency (Establishment
of Government Nuclear Emergency Response Headquarters and Local
Emergency Response Headquarters)
20:50: Fukushima Prefecture’s Emergency Response Headquarters issued a
direction regarding the accident occurred at Fukushima-Dai-ichi
Nuclear Power Station, TEPCO, that the residents living in the area
of 2km radius from Unit 1 of the Nuclear Power Station must
evacuate.(The population of this area is 1,864)
21:23: Directives from Prime Minister to the Governor of Fukushima, Mayor
of Ookuma and Mayor of Futaba were issued regarding the accident
occurred at Fukushima-Dai-ichi Nuclear Power Station, TEPCO,
‘pursuant to Paragraph 3, Article 15 of the Act on Special Measures
Concerning Nuclear Emergency Preparedness as follows:
-Residents living in the area of 3km radius from Unit 1 of the Nuclear
Power Station must evacuate.
-Residents living in the area of 10km radius from the Unit 1 must take
sheltering.
24:00: Mr. Ikeda, Vice Minister of METI, arrived at the Local Emergency
Response Headquarters
(March12)
05:22 Unit 1 of Fukushima Dai-ni notified NISA of the situation of the
Article 15 of Act on Special Measures Concerning Nuclear Emergency
Preparedness.
05:32 Unit 2 of Fukushima Dai-ni notified NISA of the situation of the
Article 15 of Act on Special Measures Concerning Nuclear Emergency
Preparedness.
05:44 Residents living in the area of 10km radius from unit 1 of the Nuclear
Power Station must evacuate by the Prime Minister Direction.
06:07 Regarding of Fukushima Dai-ni NPS, TEPCO reported NISA in
accordance with Article 15 of Act for Special Measures Concerning
6
Nuclear Emergency Preparedness.
06:50 According to the article 64, 3 of the Nuclear Regulation Act,
government order to control the internal pressure in
Fukushima-dai-ichi Units 1 and 2
07:45 Directives from Prime Minister to Governor of Fukushima, Mayors of
Hirono, Naraha, Tomioka, Ookuma and Futaba were issued regarding
the accident occurred at Fukushima-Dai-ni Nuclear Power Station,
TEPCO, pursuant to Paragraph 3, Article 15 of the Act for Special
Measures Concerning Nuclear Emergency Preparedness as follows:
-Residents living in the area of 3km radius from Fukushima Dai-ni
Nuclear Power Station (NPS) must evacuate.
-Residents living in the area of 10km radius from Fukushima Dai-ni
NPS must take sheltering
17:00 Notification pursuant to Article 15 of the Act for Special Measure
Concerning Nuclear Emergency Preparedness since the radiation
level exceeded the acceptable level of Fukushima Dai-ichi NPS.
17:39 Prime Minister directed evacuation of the residents living within the
10 km radius from the Fukushima-Dai-ni NPS
18:25 Prime Minister directed evacuation of the residents living within the
20kmn radius from the Fukushima Dai-ichi NPS
19:55 Directives from Prime Minister was issued regarding sea water
injection to Unit No.1 of Fukushima Dai-ichi NPS.
20:05 Based on the directives form Prime Minister and pursuant to
Paragragh 3, Article 64 of the Nuclear Regulation Act, the
Government issued an order to inject sea water Unit 1 of Fukushima
Dai-ichi NPS.
20:20 Fukushima Dai-chi NPS, Unit1 started sea water injection.
(March 13)
05:38 TEPCO notified NISA of the situation pursuant to the Article 15 of Act
on’Special Measures Concerning Nuclear Emergency Preparedness
‘that Unit 3 of Fukushima Dai-ichi NPS is in a loss of all coolant
injection function. Recovering efforts of the power source and coolant
injection function and work on venting are underway.
09:08 Pressure suppression in the Containment Vessel and fresh water
injection started at Unit 3 of Fukushima Daii-chi NPS.
7
09:20 Opening of Pressure vent valve of Unit 3 of Fukushima Dai-ichi NPS.
09:30 NISA directed the Governor of Fukushima Prefecture, the Mayers of
Ookuma-machi, Futaba-machi, Tomioka-machi and Namie-machi
based on the Act for Special Measures Concerning Nuclear Emergency
Preparedness on radioactivity decontamination screening.
09:38 TEPCO notified NISA that Unit 1 of Fukushima Dai-ichi NPS reached
a situation specified in Article 15 of the Act for Special Measures
Concerning Nuclear Emergency Preparedness.
13:09 Tohoku Electric notified NISA that Onagawa NPS reached a situation
specified in Article 10 of the Act for Special Measures Concerning
Nuclear Emergency Preparedness.
13:12 Fresh water injection was switched to sea water injection at Unit 3 of
Fukushima Dai-ichi NPS.
14:25 TEPCO notified NISA that Fukushima Dai-ichi NPS reached a
situation specified in Article 15 of the Act for Special Measures
Concerning Nuclear Emergency Preparedness.
(March 14)
01:10 Sea water injection at unit 1 and unit 3 of Fukushima Dai-ichi NPS
were temporary stopped due to decreasing sea water in pool
03:20 Sea water injection at unit 3 of Fukushima Dai-ichi NPS was
restarted.
04:24 TEPCO notified NISA that Fukushima Dai-ichi NPS reached a
situation specified in Article 15 of the Act for Special Measures
Concerning Nuclear Emergency Preparedness.
8
(1) Case for Travel from Futaba Public Welfare Hospital to Nihonmatsu Man
and Woman Symbiosis Center, Fukushima Prefecture
i) No. of persons to be measured: About 60 persons
ii) Measured Result: Not yet
iii) Passage: Exposure could have happened while waiting to be picked
up by helicopter at the Futaba high school ground
iv) Other
Prefectural Response Headquarters judged that there were no
exposure to 35 persons who traveled from Futaba Public Welfare
Hospital to Kawamata Saiseikai Hospital, Kawamata-machi by the
private bus provided by Fukushima Prefecture.
(2) Case for Futaba-machi Residents Evacuated by Buses
i) No. of Persons: About 100 persons
ii) Measured Result: 9 persons out of 100 persons
No. of Counts No. of Persons
18,000cpm 1
30,000″36000cpm 1
40,ooocpm 1
little less than
40,000cpm*
1
very small counts 5
*(This results was measured without shoes, though the first
measurement exceeded 100,000cpm)
iii) Passage: Under investigation
iV) Other
Though persons evacuated in different location outside of the
Prefecture (Miyagi Prefecture), all destinations are under
confirmation.

Ookuma-machi: Evacuation of subject evacuees (about 11,000 persons)
completed. (Area of Refuge: Tamura Comprehensive Gymnasium, etc.)

(Contact Person)
Mr. Toshihiro Bannai
Director, International Affairs Office,
NISA/METI
Phone:+81-(0)3-3501-1087
From: Wegner, Mary •q-‘c )
Sent: Saturday, March 12, 2011 4:05 PM
To: Beasley, Benjamin; Criscione, Lawrence; King, Mark; Thomas, Eric; Breskovic, Clarence; Bernardo, Robert; Sigmon,
Rebecca; Sigmon, Rebecca; Tabatabai, Omid
Subject: NISA in English
http://www.nisa.meti.go.mp/english/index.html note MAY you need to hit refresh to get the latest info.

Previous Article