TEPCO Claims Able To Remove Nuclear Fuel From Reactors Quicker Than Three Mile Island

Tokyo (CNN) — The decommissioning of four reactors at the crippled Fukushima Daiichi nuclear power plant will likely take more than 30 years to complete, according to a report by Japanese officials.

The draft report, released by Japan’s Atomic Energy Commission of the Cabinet Office on Friday, said the removal of debris — or nuclear fuel — should begin by the end of 2021.
“We set a goal to start taking out the debris within a 10-year period, and it is estimated that it would take 30 years or more (after the cold shutdown) to finish decommissioning because the process at Fukushima would be complicated,” the report states.

The atomic energy commission’s report noted it took 10 years to remove nuclear fuel after the 1979 Three Mile Island disaster in the United States. The commission predicted removing fuel at Fukushima would require more time because the situation is more severe.

Source: edition.cnn.com, via Twitter search for Nuclear
About author
Enformable is focused on providing critical information about energy related topics for readers around the world.The functional goal of the project is to provide a user-friendly public resource, complete with database of supporting research materials and data.Facebook Twitter
Read More About , , , , , , , , , , , , , ,
Submit your comment

Please enter your name

Your name is required

Please enter a valid email address

An email address is required

Please enter your message

*

Enformable © 2014 All Rights Reserved

More in Featured, Fukushima Daiichi
Article just published map dose radioactive contamination of tellurium and silver
Japan – MEXT Releases New Maps Show Radiation Contamination from Tellurium Found Up To 2,660,000 Bq/m3

Japan - MEXT Releases New Maps Show Radiation Contamination from Tellurium Found Up To 2,660,000 Bq/m3 And Silver Up To 83,000 Bq  - Still Less Than 16% of Cesium Alone On October 31st,...

Close