December 13th, 2011 – NFPA 805 Industry Perspectives

NFPA 805 Industry Perspectives

December 13th, 2011
Alex Marion, Vice President
Nuclear Operations
Nuclear Energy Institute

Where Are We Now?

* Transition Status:

o 48. of 104 Units Transitioning to NFPA 805
o 2 Pilot Plant Safety Evaluations
o Harris Has Implemented NFPA 805
o 6 Non-Pilot LARs Submitted To Date

* Staggered LAR Submittals

° Good Interactions With the Staff

What is Success?

” Well Defined Stable Process for LAR/SE:

o Development
o Review/Approval

* Plant Fire Safety Improvements
* Effective Implementation
* Effective Post-Transition Processes
* Effective Use of Resources

About author
Enformable is focused on providing critical information about energy related topics for readers around the world. The functional goal of the project is to provide a user-friendly public resource, complete with database of supporting research materials and data. Facebook Twitter
Read More About ,
Submit your comment

Please enter your name

Your name is required

Please enter a valid email address

An email address is required

Please enter your message

*

Enformable © 2013 All Rights Reserved

More in Nuclear Research
Enformable ML113480026_Page_01
December 15th, 2011 – Generic Licensing Topics and Policy Issues for SMRs

Generic Licensing Topics and Policy Issues for SMRs Commissioners’ Hearing Room December 15, 2011 Process • Gather input from other NRC offices, other federal agencies, and industry • Review all appropriate NRC environmental policies, guidance and regulations • Review current...

Close